GUYZANCE ROOM - STEP BY STEP PROGRESS

 

 

22 OCTOBER 2010                        FROM THIS TO THIS                  20 APRIL 2013
 

                                    

BACK ROOM - The small back room, although available for hire, was not the nicest of rooms and in need of major refurbishment.  The village Hall committee  proposed that the existing back room be pulled down and a new one re-built. Please click the appropriate links below to see what was planned
PLANNING
APPLICATION
EXISTING
PLAN
PROPOSED
PLAN

The new room will be disabled friendly, completely self contained and larger, lighter and have patio doors leading out onto the patio and community garden.    It will have its own toilet facilities and access to the kitchen.  A sub-committee has been formed to look at ways of seeking funding to fulfil this project (35,000.00). and can be viewed by following this link. Photographs of the current room can be seen below.
 
EXTERIOR AND INTERIOR OF THE SMALL WORLD WAR II BACK ROOM
                         


PREPARATION OF OLD WWII PRE-FAB BEFORE SPECIALIST DEMOLITION

THE MAJORITY OF VILLAGE HALL COMMITTEE MEMBERS AND SPOUSES
- EDDIE CRITCHLOW; BOB SMAILES; STEVE & SHARON THORPE; LORNA & GARY BUDGE; BARBARA & GRAHAM COCK; ALISON SHARPE; BARBARA KING; VIOLET CURRIE started work on removing the polystyrene ceiling tiles and clearing/sorting the two other store areas in the village hall on the evening of 18th October 2012.  Some of the photos taken by Graham Cock -

 


  
       
      

      


 


 

The names above were found written on the floor in the far top left corner of the room after the carpet had been removed. 
All dated from 1981.

 

PROGRESS OF THE RE-BUILD IS SHOWN IN THE PICTURES BELOW IN REVERSE ORDER.

 4 APRIL 2013 - CLASSIC OAK FLOORING          20 APRIL 2013 - ACCESS RAMP COMPLETED    30 MAR 2013 - REAR OF ROOM                                                                 
     

     30 MAR 2013 - TOILET IN AND WORKING 
23 MAR 2013 - CEILING LIGHTS WORKING   30 MAR 2013 - WALLS PAINTED
                                                                                                                                                                                                     (SULTANA SPICE)


     
 

13 MAR 2013 - PLASTERBOARDS FITTED         23 MAR 2013 - KITCHENETTE FITTED         7 MAR 2013 - WINDOWS/DOORS FITTED

        

  12 MAR 2013 - ROOF INSULATION 6" THICK           28 FEB 2013 -TILING HIGH                              3 MAR 2013 - TILING COMPLETED

       


          16 FEB 2013 - ROOF FELTED                        28 FEB 2013 - ROOF TILING BEGUN                JAN 2013 - WALLS PROGRESSING

       

       9 FEB 2013 - ROOF JOISTS FITTED           JAN 2013 - OUTER WALLS PROGRESSING    JAN 2013 - FLOOR JOISTS IN PLACE
                                                                                               
       

NOV 2012 - DAMP-PROOFING COURSE
            DEC 2012 - OUTER SHELL OF NEW BUILD   NOV 2012 - CONCRETE FOUNDATIONS  
FINISHED
                                                                  STARTED                                                                                      BEGUN
       

    NOV 2012 - DAMP-PROOFING COURSE      NOV 2012 - WHERE DID THE LIGHT GO IN NOV 2012 - THE CULPRIT BLOCKING ALL THE
                           LAID                                                                     THE KITCHEN                                                       LIGHT IN THE KITCHEN
       

    NOV2012 - DEMOLITION ALMOST                   NOV 2012 - DIGGING FOUNDATIONS       NOV 2012 - "A STEAMING HOT CURRIE!"  
                         COMPLETED                                                                                                                                    
       

    NOV 2012 - LIAM O'DONNELL "WISH I'D        25/10/2012 - THE ROOF IS OFF                   1/11/2012 - THE FIRST WALL DOWN
                          WORN MY SUIT NOW"
     
 

    OCT 2012 - The Asbestos Removal          
OCT 2012 - SPECIALIST ASBESTOS
                          Firm
 ON SITE                                     REMOVAL TEAM REMOVING ROOF